Rooftop Solars At Matunga Workshop Leads The Way In Green And Sustainable Railway Operations

Rooftop Solars At Matunga Workshop Leads The Way In Green And Sustainable Railway Operations

2 MW Rooftop Solar Capacity / No Upfront Capital Investment by Railways / Annual Projected Generation of 28.56 Lakh Units / Annual Electricity Savings of ₹1.90 Crore


Mumbai shrekesh Choubey:-
Central Railway’s Matunga Workshop, one of the oldest railway workshops in India, is taking significant steps towards sustainable railway operations through the adoption of renewable energy and energy-efficient practices.

Established in 1915 during the period of the erstwhile Great Indian Peninsula (GIP) Railway, the workshop has completed more than a century of dedicated service to Indian Railways. Initially established for the maintenance and repair of broad-gauge and narrow-gauge coaches and wagons, the workshop has continued to upgrade its infrastructure and facilities over the years.

As part of Indian Railways’ commitment towards achieving Net Zero Carbon Emissions by 2030, Matunga Workshop has made effective use of the available rooftop space by installing solar power plants with a capacity of 2 MW. This initiative is a significant step towards meeting the workshop’s energy requirements through clean and renewable sources.

The rooftop solar plant has been developed under the RESCO model, without any upfront capital investment by Railways. The developers have made the investment towards installation of the solar plants and are responsible for their operation and maintenance as per the contractual provisions. Railways procure the solar power generated at the agreed Power Purchase Agreement (PPA) rates.

Two grid-connected rooftop solar power plants with a combined AC capacity of 2 MW have been installed under the RESCO model. The first solar plant, developed by M/s S.G. Renewables, New Delhi was commissioned in February 2020, with a capacity of 1,000 kW. The second plant, developed by M/s Comspec Renewable, Hyderabad was commissioned in March 2026, with a capacity of 1,000 kW.

The two plants comprise:
– Total DC capacity: 2,300 kWp
– Total AC capacity: 2,000 kW
– Total solar modules installed: 5,448
– Total inverters: 35
– Net metering facility available for both plants

The solar plants are projected to generate approximately 28.56 lakh units of electricity annually. This is estimated to meet around 42.5% of the workshop’s total electricity requirement, thereby reducing its dependence on conventional grid power and increasing the share of renewable energy in its operations.

The initiative is to provide substantial financial benefits to Indian Railways, the annual saving in electricity expenditure is projected at approximately ₹1.90 crore.

In addition to the financial benefits, the rooftop solar installations are expected to avoid approximately 2,340 metric tonnes of CO₂ emissions annually. This will contribute towards reducing the carbon footprint of workshop operations and promoting a cleaner environment.

The solar plants are equipped with online remote monitoring facilities to track generation and operational performance. Regular monitoring of generation, verification with electricity bills and scheduled cleaning of solar modules are being undertaken to ensure efficient operation and sustained performance.

The rooftop solar initiative at Matunga Workshop demonstrates the effective utilisation of existing Railway infrastructure for renewable energy generation. It serves as a positive example of how Railway establishments can reduce conventional energy consumption, achieve recurring financial savings and contribute towards the environmental sustainability goals of Indian Railways.

It is worthwhile to mention that the PMO has set a target of 10.33 MWp for the installation of rooftop solar plants in Central Railway. A total of 14.79 MWp of rooftop solar capacity has already been commissioned in Central Railway. The total commissioned rooftop solar capacity in Central Railway now stands at 22.68 MWp.